December 8, 2012 - Signed Contract
December 13, 2012 – Preliminary Approval from First Home Mortgage
December 12, 2012 - Met SR to go over options
December 22, 2012 – Picked our brick and colors
December 27, 2012 – Picked Flooring/carpet options
December 29, 2012 – picked multimedia /audio options thru CV security
January 24, 2013 – Lot change from 14 to 6
February 4, 2013 - Pre-construction Meeting
February 18 – Estimated time for construction to start!
February 18, 2013 - Lot was staked
February 20, 2013 - Backhoe delivered to lot
February 22, 2013 - Lot is cleared, placed the gravel driveway and new Silt Fence was installed.
February 23, 2013 - Brick color changed
__________________________________________________________________________________
Start of Construction
March 4 - 9, 2013
Day 1- Excavation
Day 2- Footers
Day 3- Nothing SNOW
Day 4- Foundation Walls Framed
Day 5- Foundation Walls Poured
Day 6- Foundation forms removed
March 10- 16, 2013
Day 7- Nothing
Day 8- Nothing
Day 9- Waterproofing started.
Day 10- Nothing
Day 11- Plumbing / Locked our Rate 3.5%
Day 12- Nothing
Day 13- Waterproofing finished and gravel started to be poured
March 17- 23, 2013
Day 14- Nothing
Day 15- Nothing
Day 16- Backfilled started / USDA Approval!!
Day 17- Underground Plumbing Inspection Approved!
Day 18- Nothing
Day 19- Wood Delivered!!
Day 20- gravel poured on basement and garage floors
March 24- 30, 2013
Day 21- Forms and rebar placed for cement floors in basement and garage
Day 22-nothing
Day 23- Inspection of floors and rebar Approved
Day 24- Cement Floors poured
Day 25- More wood delivered
Day 26- Roof Delivered
Day 27- Nothing
March 31- April 6, 2013
Day 28- Easter Nothing
Day 29- Stinky Nothing PM/SR sucks no communication
Day 30- Beams laid and Framing started
Day 31- First floor walls done and interior walls almost done!!
Day 32- First floor completed and floor started on 2nd Floor
Day 33- 2nd Floor flooring completed
Day 34- Nothing
April 7- 12, 2013
Day 35- Nothing
Day 36- 2nd Floor walls up
Day 37- Roof Trusses installed
Day 38- Half of roof covered with plywood
Day 39- Roof covered in Plywood shingles delivered
Day 40- Rain delay dumpster delivered
Day 41- Shingles installed.
April 14- 20, 2013
Day 42- Nothing
Day 43- Steps insulation started, garage doors framed
Day 44- Garage steps and trim installed and cleaned up!
Day 45- Windows, doors and wrap started.
Day46- More windows installed. 1st layer of wrap
Day 47- Main stairs installed, windows taped, HVAC markings
Day 48- Nothing
April 21- 27
Day 49- Nothing
Day 50- Brick and scaffolding delivered
Day 51- Nothing
Day 52- Electrical started, PVC pipes delivered, final wrap installed. work order change to include eyeball lights and stair stain to cherry. Met with PM to go over Master bath framing
Day 53- Brick started, plumbing installed as well as bathtubs & hot water heater
Day 54- More Brick
Day 55- More Brick
April 28- May 4th
Day 56- Nothing
Day 57- Nothing
Day 58- Brick, HVAC and more electrical work
Day 59- Brick finished
Day 60- More electrical work
Day 61- Windows fixed in Solarium
Day 62- Nothing
May 5th - May 11th
Day 63- Nothing
Day 64- Pre wiring meeting with CV Security, Sprinklers started, more electrical work
Day 65- Wrote verses on walls
Day 66- Finished verses on walls Finished electrical work
Day 67- Pre Drywall meeting, sprinklers finished
Day 68- Electrical inspection Passed/ Corrections made from pre drywall meeting
Day 69- Nothing
May 12th- May 18th
Day 70- Nothing
Day 71- Inspections for Electrical and Framing
day 72- Insulation installed
Day 73- Insulation installed
Day 74- Failed Energy test, Dirt hauled away
Day 75- Passed Energy star test
Day 76- Drywall Installed
May 19th- May 25th
Day 77- Nothing
Day 78- Siding started
Day 79- Mudded
Day 80- Siding, Trim and shutters finished
Day 81- Mudded and Sanded, interior doors, trim and paint delivered.
Day 82- Cabinets delivered, trim installed
Day 83- Nothing
May 26th- June 2nd
Day 84- Nothing
Day 85- Painting, water ran to house
Day 86- Cabinets installed
Day 87- Electrical work
Day 88- Painting
Day 89- Nothing
Day 90- Nothing
June 3rd- 8th
Day 91- Tile started, railings started, gas line ran to house
Day 92- Tile finished, fixtures installed, sink faucets, carpet installed
Day 93- Driveway and front steps poured, outside units installed
Day 94- Railings finished, more electrical work, appliances started
Day 95- Paint touched up, more appliances installed, closet shelves installed, more electrical
Day 96- Nothing
June 9th- 15th
Day 97- Gutters Installed
Day 98- Nothing
Day 99- Fridge installed
Day 100- Sod installed, Door painted, 2nd coat of stain on steps
Day 101- Inspections
Day 102- U&O and Final Appraisal!
Day 103- Nothing
June 16th- 18th
Day 104- Nothing
Day 105- Final Walk Thru
Day 106- June 18th Closing 10:00 AM!!!!!
________________________________________________________________________
Living in Home
June 19, 2013